Abstract/Summary
The project objective was to: identify ways to reduce the production cost of Cal Poly Chocolates. The project was executed through the DMAIC approach, a data driven improvement cycle. Using several industrial engineering tools, six improvement opportunities were found. Three project deliverables were created and three process changes were recommended. The total annual savings, if recommendations are implemented, sum to $1700.